8 machines can do a piece of work in 10 days. How long will it take 16 machines to do the work?

✔ Correct Answer: A. 05 days

The correct answer to the question “8 machines can do a piece of work in 10 days. How long will it take 16 machines to do the work?” is 05 days. This question belongs to Mathematics. Practice the related questions below to master this topic for your FPSC, PPSC and NTS tests.

Related MCQs

complete the series: 4.8.9.13.14.18.____?Find out the wrong number in the series : 1, 1, 2, 6, 24, 96, 720Find the average of the series : 312, 162, 132, 142 and 122?Find the Missing Number in the series 1, 6, 13, 22, 33 ?In a school, 40 % of the students play football and 50 % play cricket. If 18 % of the students play neither football nor cricket, the percentage of students playing both is____?