If 40 men build 4 buildings in 12 months how many men would be required to build 6 houses in 4 months​?

✔ Correct Answer: C. 180 men

The correct answer to the question “If 40 men build 4 buildings in 12 months how many men would be required to build 6 houses in 4 months​?” is 180 men. This question belongs to Mathematics. Practice the related questions below to master this topic for your FPSC, PPSC and NTS tests.

Related MCQs

complete the series: 4.8.9.13.14.18.____?Find out the wrong number in the series : 1, 1, 2, 6, 24, 96, 720Find the average of the series : 312, 162, 132, 142 and 122?Find the Missing Number in the series 1, 6, 13, 22, 33 ?In a school, 40 % of the students play football and 50 % play cricket. If 18 % of the students play neither football nor cricket, the percentage of students playing both is____?