The bridge is completed in 45 days by 105 men. How it will take 90 men to do the work?

✔ Correct Answer: A. 52 1/2

The correct answer to the question “The bridge is completed in 45 days by 105 men. How it will take 90 men to do the work?” is 52 1/2. This question belongs to Mathematics. Practice the related questions below to master this topic for your FPSC, PPSC and NTS tests.

Related MCQs

complete the series: 4.8.9.13.14.18.____?Find out the wrong number in the series : 1, 1, 2, 6, 24, 96, 720Find the average of the series : 312, 162, 132, 142 and 122?Find the Missing Number in the series 1, 6, 13, 22, 33 ?In a school, 40 % of the students play football and 50 % play cricket. If 18 % of the students play neither football nor cricket, the percentage of students playing both is____?